Renovations on the west side of Neyland Stadium will begin starting Friday, December 1st, and will continue through August 2024. In addition, a steam line replacement project will start in February 2024. Both of these construction events necessitate a partial closure of Phillip Fulmer from Gate 20 to the G10 garage.
Map of partial Phillip Fulmer closure with pedestrian paths
Phase 1 – The Neyland Stadium Renovation
- Initial partial closure of Phillip Fulmer Way from Gate 20 to Gate 15 will begin Friday, December 1st
- On-street commuter parking from Peyton Manning south to the G10 garage will close
- The G10 garage off Fulmer will have limited access. We are strongly encouraging special event attendees, basketball permit holders, visitors for commencement, etc to enter and exit the G10 garage from Neyland Dr.
- The Fort and Neyland Express buses will be rerouted
- New special event maps
- Pedestrian paths will be created and adjusted throughout the closure
- Staff parking impacts:
- S9 – both entrances will be open, but the intersection of Peyton Manning and Phillip Fulmer will be closed
- S30 entrances – The P1 entrance and the G5/30 entrance off Phillip Fulmer will remain open to local traffic.
Phase 2 – Steam Line Replacement
- Phillip Fulmer Way closure now extends to the G10 garage entrance off Phillip Fulmer
- The G10 garage at Phillip Fulmer will close. The only access to this garage will be from Neyland Dr
- Staff parking impacts:
- S9 – both entrances will be open, but the intersection of Peyton Manning and Phillip Fulmer will be closed
- S30 P1 entrance is expected to be open but may be impacted when the Steam Line construction equipment is by the G10 entrance in Feb.
- The G5/30 entrance from Phillip Fulmer will close