Skip to content Skip to main navigation Report an accessibility issue

South Stadium Project temporarily closes G10 entrance off Neyland starting May 24th

Neyland Stadium renovations ramp up after Spring 2023 semester ends

Please be mindful of navigating the area around Neyland Stadium and the G-10 garage this summer

Starting on May 24th, lane closures, a garage entrance closure, utility work, and lane shifts impact mobility about the South Neyland Stadium renovations (click here for map)

  1. G10 garage entrance off Neyland Dr will be closed starting May 24th and this entrance is scheduled to reopen mid-August.
    The Phillip Fulmer entrance to G-10 will remain open all summer.
  2. Phillip Fulmer Way near the G10 gate will close curb lanes on the east side to assist with utility work. Additional intermitent lane shifts may occur and alternative pedestrian paths will be clearly marked.

The contractors will accommodate special events like concerts during the summer. The scheduled re-opening will be mid-August.